Construction Rental Finder

Rental Guide

Utility Locates Before Digging: Texas811, City Lines and Permits

Renting an excavator, mini excavator or trencher starts a clock. If the locate marks aren't on the ground when the machine arrives, it sits idle, or worse, someone digs anyway. Texas law sets the minimum notice, but many North Texas cities add their own locate step for City-owned water, sewer and signal lines.

This guide walks through the statewide rule, the city layer, and how to schedule both around a rental. It does not give legal advice; confirm requirements with Texas811 and the city for your site.

Updated

Mini excavator on a lawn with colored utility locate paint lines and flags, houses behind

The Short Answer

  • Texas Utilities Code sec. 251.151 requires notice through the one-call system no earlier than 14 days and no later than 48 hours before excavating, excluding weekends and legal holidays.
  • Many cities locate their own water and sewer lines separately; some state plainly that 811 does not mark them.
  • Work in the public right-of-way usually needs a city permit too, and some cities tie their locate request to that permit.
  • Schedule the excavator's delivery after the marks are confirmed, and keep OSHA trench rules in the plan once digging starts.

The Texas Rule: Notice Before You Excavate

Texas Utilities Code chapter 251 requires an excavator to notify the one-call notification system before excavating. Under section 251.151, notice must be given no earlier than the 14th day and no later than 48 hours before the excavation starts, not counting Saturdays, Sundays and legal holidays.

Texas811 is the one-call center most contractors use. It accepts requests by calling 811 or online, and it asks for at least two business days before digging. The ticket goes to member utility operators, who mark their lines.

  • Count only business days: a Friday afternoon request does not clear a Monday morning dig.
  • Describe the dig area precisely so operators mark the right place.
  • Keep the ticket number on site; some city permits ask for it.
  • Wait for every notified operator to respond before digging.

City-Owned Lines Often Need a Separate Request

The statewide system does not always reach City-owned infrastructure. Several DFW cities spell out a separate step:

How some DFW cities handle their own locates
CityWhat the City says
North Richland Hills811 does not mark City-owned water or sewer lines; an approved ROW permit serves as the request for City locates, and excavation begins only after 811 clears the site and the permit is issued.
DeSotoThe ROW application requires 48 hours' notice for City water, sewer and sign or signal locates, all complete before the project starts, and the permit does not replace contacting the one-call system.
ArlingtonSeparate City locates are requested at least two working days ahead; private services and storm pipes are not marked.
FriscoCity lines are not part of 811; City locates are needed for digging deeper than 18 inches, require an active ROW, TxDOT or irrigation permit, and are not done on private property.
Summaries of each City's published material as checked for this guide. Confirm current procedures with the City before digging.

Private lines are another gap. Arlington's manual notes that private services are not marked by the City. Service lines on private property, irrigation, site lighting and private storm drains may need a private locator.

Right-of-Way Permits Come First

Digging in a street, alley, sidewalk or utility easement usually needs a city right-of-way permit in addition to locates. The details vary by city:

  • North Richland Hills requires a ROW permit for any construction, maintenance or excavation in the right-of-way, asks for two to three business days of review, and requires the permit to be displayed on site.
  • DeSoto requires plans and a traffic control plan sealed by a Texas professional engineer, mechanical compaction of all ROW excavations with test reports, and temporary security fencing around open excavations overnight.
  • Rowlett will not issue ROW permits to contractors that are not registered with the City.
  • Wylie takes right-of-way construction permits and contractor registration online through its CitizenServe portal.

See the city pages for Rowlett and Wylie for links to each City's process.

Fitting Locates Into a Rental Schedule

The most common scheduling mistake is booking the machine for the day the ticket is filed. Work backward from the first dig:

Example sequence for a utility tie-in
StepWhat to confirm
PermitROW or grading permit applied for and issued, with any traffic control plan approved.
Texas811 ticketFiled at least two business days ahead, within the 14-day window.
City locatesRequested as the City directs, sometimes through the permit itself.
Marks verifiedEvery operator responded; private lines located if needed.
Machine deliveryExcavator, trencher or mini excavator arrives after marks are verified.
Illustrative sequence. Lead times vary by city, permit type and season.

City hours can push the window further. Euless treats building excavation outside 7 a.m. to 6 p.m. on weekdays as a noise nuisance, and Wylie requires a permit and a City inspector for Saturday work on engineering permits. A ticket that clears on a Friday may not mean a Saturday dig.

For choosing the right machine once the marks are in, see what size excavator do I need and skid steer vs mini excavator.

Once Digging Starts

Locates tell you where lines are, not how deep. Expose marked lines carefully near the marks, and stop to call the operator if you find an unmarked line or damage one.

OSHA's trenching rules apply as soon as a trench gets deep enough. OSHA's fact sheet calls for protective systems in trenches 5 feet deep or more unless the excavation is in stable rock, a design by a registered professional engineer for trenches 20 feet deep or more, spoils and other loads kept at least 2 feet from the edge, and daily inspection by a competent person.

  • Keep the excavator's spoil pile back from the trench edge.
  • Plan access and egress before the trench is open.
  • Backfill and compact to the City's specification; DeSoto requires mechanical compaction and test reports for ROW excavations.
  • Restore pavement, sod and sprinklers as the permit requires.

The site preparation equipment guide covers trenchers, compactors and loaders for the rest of the job.

Specifications are taken from manufacturers' published materials and can change. This guide is general information. Always follow the manufacturer's instructions, your rental provider's requirements and your jobsite's safety rules.

FAQ

Frequently Asked Questions

How far ahead do I have to call 811 in Texas?

Texas Utilities Code section 251.151 requires notice no earlier than 14 days and no later than 48 hours before excavating, not counting weekends and legal holidays. Texas811 asks for at least two business days.

Does 811 mark city water and sewer lines?

Not always. North Richland Hills, for example, states that 811 does not mark City-owned water or sewer lines, and DeSoto requires a separate City locate request with 48 hours' notice. Check the city's process for your site.

Do I need a permit to dig in the right-of-way?

Usually. Cities such as North Richland Hills, DeSoto, Rowlett and Wylie require a right-of-way permit for work in streets, alleys and easements, in addition to locates.

When should the rental excavator arrive?

After the permit is issued and every locate is marked and verified. Booking the machine for the day the ticket is filed often means paying for idle days.

Find Equipment for Your Project

Browse equipment categories with rental considerations and FAQs for each.

Browse Equipment